Update by Purchaser Calvin Leong – Oct 30, 2009
Purchaser Calvin Leong has updated us on the discussion, here it goes:-
I would like to update about the optional package:
They have finalize the tender for optional package.
- air-cond will be York (forgot to ask what HP)
- the would install the furniture along with handover
- for home automation item, one of the feature is intercom system will not only connect to the guardhouse, it will connect directly to your mobile.
- (I think) they have done the piping for centralize hot water and we just have to source for a water heater and install it (for those who didn’t sign up for optional package 2). Pls don’t take my word for this.
Thanks to Calvin Leong.
Related topics:-
1. Update by Purchaser Au – Oct 30, 2009
30
2009
Update by Purchaser Au – Oct 30, 2009
Calvin Leong, Au and I met with the Bukit Ikhlas management yesterday. Here is purchaser Au’s update on our discussion:-
Dear all,
Bayan Villa is now in the process of QA/QC the units before handing over to the purchasers. They are actually doing the defect works for us, in maintaining high quality of works carried out by their contractors. Broken or smeared tiles, will be replaced with new ones and be assured that this will be completed soon enough as Bayan Villa has employed sufficient workforce to carry out the task.
I’ve briefly checked on the few units on Wednesday (28 Oct), and found that the workforce is diligently doing the rectification works, and no worries for all of us that the quality is up to the standard. It’s also good that they do it now instead of us finding out and later on filling up the defect work forms when we want to move in.
There will be some news on Sam’s blog about commitment given by Bayan Villa some time from now, but please do give time allowance to update the info on his blog.
Regards,
Au
Thanks to Au.
14
2009
Progress update by Stages
| No. | Stage | % | Remark |
|---|---|---|---|
| 1 | Immediately upon the signing of the Agreement | 10 | Done |
| 2 | Within twenty-one (21) working days after receipt by the Purchaser of the Vendor’s written notice of the completion of: | - | - |
| 2 (a) | the work below ground level including piling and foundation of the said Building comprising the said Parcel | 10 | Done |
| 2 (b) | the reinforced concrete framework and floor slab of the said Parcel | 15 | Done |
| 2 (c) | the walls of the said Parcel with door and window frames placed in position | 10 | Done |
| 2 (d) | the roofing/ ceiling, electrical wiring, plumbing (without fittings), gas piping (if any) and internal telephone trunking and cabling to the said Parcel | 10 | Done |
| 2 (e) | the internal and external plastering of the said Parcel | 10 | Done |
| 2 (f) | the sewerage works serving the said Building | 5 | Done |
| 2 (g) | the drains serving the said Building | 5 | Done |
| 2 (h) | the roads serving the said Building | 5 | Done |
| 3 | On the date the Purchaser takes possession of the said Parcel with water and electricity supply ready for connection to the said Parcel | 12.5 | |
| 4 | Within twenty-one (21) working days after receipt by the Purchaser of the written confirmation of the Vendor’s submission to and acceptance by the Appropriate Authority of the application for subdivision of the said Building | 2.5 | |
| 5 | On the date the Purchaser takes vacant possession of the said Parcel as in items 3 and to be held by the Vendor’s solicitor as stakeholder for payment to the Vendor as follows: (a) two point five per centum (2.5%) at the expiry of six (6) months after the date the Purchaser takes vacant possession of the said Parcel (b) two point five per centum (2.5%) at the expiry of eighteen (18) months after the date the Purchaser takes vacant possession of the said Parcel |
5 | |
| 80% Done | |||