Update by David of Bukit Ikhlas – June 23, 2009
1. Pengarah Ismail has submitted the relevant report to the statutory authorities, TNB, JKR, IKRAM etc…
2. CCTV to start this week.
3. Suction Tank at Jabatan Pertanian, across Tmn Uni Indah in progress.
4. Access Road – behind Sri Pinang, piliing work completed, roadwork to commence. Foundation work started near retention pond.
5. TNB started coring work from Commercial ctr through (underneath road ) to old guard house area
6. Optional Packages – meeting with Architect this Thursday.
7. Units – both internal & external – ongoing touch up rectification.
02
2009
Reply from David Teng, the spokeperson of Bukit Ikhlas
David Teng, the spokeperson from the management of Bukit Ikhlas has replied us, but it doesn’t help to boost the progress of the development, delay means delay. Let me summarize David’s reply for your reading pleasure.
According to David, the physical construction of the units has been completed, and they have been progressively receiving keys from the main contractors. But he added that they were having issues with the statutories authorities, who keep changing and adding to their (statutories authorities) requirements.
I am not sure if it is good for me to reveal the details of David’s reply, especially on the Syabas and MPSJ related matters. Anyway, the purchasers have requested a meeting with Bukit Ikhlas to be arranged as soon as possible.